Engineering

Permits, inspections, and engineering contracts

Data source: November 2026 SITREP

Engineering Contracts (IDIQ)

Federal & State Inspections

CPRA Quarterly Inspection

GREEN

State-mandated quarterly visual inspection of the levee system, with findings reported to the Coastal Protection and Restoration Authority.

34%
Actual: Q3 field inspections complete and under Engineering review; Q4 field inspections underway
Expected: 34% by report date (100% by end of quarter)
Q4 2026
Mandate: CPRA
CPRA submission date pending

USACE Semi-Annual Report

GREEN

Federal inspection of HSDRRS levees, floodwalls, PCCPs, and complex structures. 100% = on pace for this point in the half-year cycle.

100%on pace
Actual: 100% complete · FPA submitted its portion to CPRA on 10/17/2026; CPRA subsequently submitted the entire report to USACE on 11/02/2026
Expected: Target: 67% by today, 100% by end of half
Semi-Annual · Ongoing
Mandate: USACE
Submission pending

Current Capital Projects

Major capital projects currently under contract, in construction, or in active bidding.

Foreshore Erosion Repair

In Bidding

Bid openings occurred on 10/29/26. Lowest Bid was $53,254,217. USACE project award / contract execution ongoing.

Source: November 2026 SITREP

LPV Access Bridge

In Progress

Construction has begun. Construction progressing and on schedule.

Source: November 2026 SITREP

Orpheum Slope Paving

In Progress

Project is substantially complete. Contract closeout ongoing.

Source: November 2026 SITREP

Franklin Ave. Vault 4 – Final

In Progress

Project is substantially complete. Contract closeout ongoing.

Source: November 2026 SITREP

London Avenue Canal Erosion Mitigation (Phase 1)

In Progress

Full NTP issued on 10/12/26 with an expected start of activities within the canal around 11/1/26.

Source: November 2026 SITREP

40 Arpent Sheet Pile Rehabilitation (Phase 2)

In Design

60% design submittal currently under review by Engineering.

Source: November 2026 SITREP

Franklin Herbicide Vehicle Containment

In Progress

Construction is 95% complete.

Source: November 2026 SITREP

Lakeshore Drive Flood Warning Signs

In Design

60% Design submitted. Review comments have been forwarded to designer. 90% design underway.

Source: November 2026 SITREP

Franklin Facility Access Improvements

In Design

60% Design submittal reviewed by Engineering. Plans are currently being reviewed by other FPA stakeholders.

Source: November 2026 SITREP

Tropical Storm Arthur – Franklin Facility Damage

In Design

Demolition work has been completed. Secondary structural inspection completed (awaiting results). Final repair design scope being determined.

Source: November 2026 SITREP

Permits

Permit Overview

Life of a permitView permit data

Permit Submittal
FPA-E Review
External Agency Coordination
Receipt of LNO
Final Review
Permit Issued

Source: FPA Engineering Department

Monthly Permits Issued

Months without a published SITREP count are left blank.

MonthPermits IssuedSource
October 202615November 2026 SITREP
September 202632November 2026 SITREP
August 202629November 2026 SITREP
July 202633August 2026 SITREP
May 202619June 2026 SITREP
April 202627May 2026 SITREP
March 202627Apr 2026 SITREP
February 202625Mar 2026 SITREP
January 202642Feb 2026 SITREP
December 202510Jan 2026 SITREP
November 202546Dec 2025 SITREP
October 202550Nov 2025 SITREP
September 202525Oct 2025 SITREP

Source: SITREPs

Routine Maintenance Activities

Current Maintenance Work

  • Completed 24 earthen levee repairs from in-house work orders
  • Completed 27 floodwall surface spall repairs on sections, joints, and slope pavement
  • Hurricane gate annual inspections 45% complete
  • Q1 2026 valve inspections and exercises complete
  • Deslonde Street levee access gate installed
  • New wiring installed at police station for camera monitors; chiller 3 water meter installed with weekly usage tracking
  • Assisting CPRA with 500-tree planting for ongoing mitigation project

Source: Apr 2026 SITREP