Engineering
Permits, inspections, and engineering contracts
Data source: November 2026 SITREP
Federal & State Inspections
CPRA Quarterly Inspection
State-mandated quarterly visual inspection of the levee system, with findings reported to the Coastal Protection and Restoration Authority.
USACE Semi-Annual Report
Federal inspection of HSDRRS levees, floodwalls, PCCPs, and complex structures. 100% = on pace for this point in the half-year cycle.
Current Capital Projects
Major capital projects currently under contract, in construction, or in active bidding.
Foreshore Erosion Repair
In BiddingBid openings occurred on 10/29/26. Lowest Bid was $53,254,217. USACE project award / contract execution ongoing.
Source: November 2026 SITREP
LPV Access Bridge
In ProgressConstruction has begun. Construction progressing and on schedule.
Source: November 2026 SITREP
Orpheum Slope Paving
In ProgressProject is substantially complete. Contract closeout ongoing.
Source: November 2026 SITREP
Franklin Ave. Vault 4 – Final
In ProgressProject is substantially complete. Contract closeout ongoing.
Source: November 2026 SITREP
London Avenue Canal Erosion Mitigation (Phase 1)
In ProgressFull NTP issued on 10/12/26 with an expected start of activities within the canal around 11/1/26.
Source: November 2026 SITREP
40 Arpent Sheet Pile Rehabilitation (Phase 2)
In Design60% design submittal currently under review by Engineering.
Source: November 2026 SITREP
Franklin Herbicide Vehicle Containment
In ProgressConstruction is 95% complete.
Source: November 2026 SITREP
Lakeshore Drive Flood Warning Signs
In Design60% Design submitted. Review comments have been forwarded to designer. 90% design underway.
Source: November 2026 SITREP
Franklin Facility Access Improvements
In Design60% Design submittal reviewed by Engineering. Plans are currently being reviewed by other FPA stakeholders.
Source: November 2026 SITREP
Tropical Storm Arthur – Franklin Facility Damage
In DesignDemolition work has been completed. Secondary structural inspection completed (awaiting results). Final repair design scope being determined.
Source: November 2026 SITREP
Permits
Life of a permitView permit data
Source: FPA Engineering Department
Monthly Permits Issued
Months without a published SITREP count are left blank.
| Month | Permits Issued | Source |
|---|---|---|
| October 2026 | 15 | November 2026 SITREP |
| September 2026 | 32 | November 2026 SITREP |
| August 2026 | 29 | November 2026 SITREP |
| July 2026 | 33 | August 2026 SITREP |
| May 2026 | 19 | June 2026 SITREP |
| April 2026 | 27 | May 2026 SITREP |
| March 2026 | 27 | Apr 2026 SITREP |
| February 2026 | 25 | Mar 2026 SITREP |
| January 2026 | 42 | Feb 2026 SITREP |
| December 2025 | 10 | Jan 2026 SITREP |
| November 2025 | 46 | Dec 2025 SITREP |
| October 2025 | 50 | Nov 2025 SITREP |
| September 2025 | 25 | Oct 2025 SITREP |
Source: SITREPs
Routine Maintenance Activities
Current Maintenance Work
- Completed 24 earthen levee repairs from in-house work orders
- Completed 27 floodwall surface spall repairs on sections, joints, and slope pavement
- Hurricane gate annual inspections 45% complete
- Q1 2026 valve inspections and exercises complete
- Deslonde Street levee access gate installed
- New wiring installed at police station for camera monitors; chiller 3 water meter installed with weekly usage tracking
- Assisting CPRA with 500-tree planting for ongoing mitigation project
Source: Apr 2026 SITREP